TC Energy Corp. is aiming to capitalize on the surging demand for natural gas in Alberta, revealing plans on Monday to enhance its pipeline infrastructure that spans much of the province.
The Calgary-based firm is introducing a proposed pipeline named the Alberta Growth Connector, which will cover approximately 370 kilometers from west to east. This initiative aims to provide an initial capacity of one billion cubic feet per day, primarily benefiting the oilsands sector in the northeastern part of the province.
This venture will be part of a more extensive strategy to expand TC’s NGTL system, which has been operational for nearly 70 years, creating an extensive network throughout Alberta and into northeastern British Columbia.
“The increasing demand for natural gas across Alberta highlights NGTL’s importance as a foundational element of TC Energy’s operations and a key platform for future expansion,” stated CEO Francois Poirier in a press release on Monday.
TC forecasts that total demand for NGTL will rise by approximately 25% to reach 18 billion cubic feet per day by 2031, which is eight percent higher than its earlier prediction for 2025. The majority, over 60%, of this demand surge is anticipated to stem from the oilsands, electricity generation, and data centers.
The expansion plan may also involve additional loops and compressor units to enhance the throughput of the current system.
“Our strategy is intentional and methodical: we intend to utilize our existing infrastructure, align investments with customer commitments, and advance projects that align with our risk and return criteria,” Poirier elaborated.
In the last ten years, TC has invested upwards of $15 billion into its NGTL system. The proposed expansions depend on obtaining commercial backing, engaging with rights holders and stakeholders, receiving regulatory approvals, and completing the company’s internal sanctioning process.
Alberta is seeking to attract data center developers to establish operations within the province, but it requires these entities to generate their own power to prevent overwhelming the provincial grid. Many current proposals include plans for nearby power plants that could significantly increase demand.
Simultaneously, the province aims to double its oil production over the next decade, necessitating a higher supply of natural gas to support new operations in the oilsands.
A confidential cabinet document from Alberta, leaked in September, expressed concerns regarding NGTL’s capability to satisfy the requirements of these emerging growth areas, labeling TC’s market dominance as a “market failure.”
In response, TC stated that collaboration among government, industry, customers, and regulators is essential to identify a solution.